SK702 Embankment Remediation Project
About the project
Scope
Removal and replacement of contaminated ballast
Realigning of stacker and reclaimer mono-rail
Construction of new drainage to limit future contamination
Construction of a temporary haul road alongside stockpile and embankment
Unbolting of tie-rod from rail and cutting tie-rods
Removing all rail and sleepers
Excavation of ballast
Shaping of sub-ballast capping
Installation of clean screened ballast to bottom of sleeper
Reinstallation of sleepers
Reinstallation of rail, re-clip, weld and grind
Construction of an upstream concrete spillage slab
Reshaping of road from edge of conveyor to new concrete spillage slab
Outcomes
BMD worked efficiently to establish the site, incorporating detailed planning to ensure the project commenced on time. This included careful logistics and transport for the required resources on the project with the team working proactively with the client to manage the project of works and ensure adequate scheduling of resources within the roster. The result was a flexible system which enabled all or some staff to allow for changes in the works and critical path activities to continue.
The project team identified opportunities to utilise both local suppliers for equipment requirements as well as employing operators for equipment as required, on a case by case basis aligned with the program of works to ensure operations were able to be maintained.