Buildings

Port of Brisbane Cement Plant Works

Location
Port of Brisbane, Brisbane, Queensland
Value
$23 million
Client
Southern Cross Cement Ltd
Status
Complete
BMD Constructions_Cement Plant Works_Queensland

About the project

BMD Constructions was contracted to complete piling and civil works for six cement silos across two independent structures, as part of the receival, in loading, storage, and out loading system for the Southern Cross Cement Pty Ltd Cement Terminal.

Scope

Earthworks and excavation works

Road widening works to facilitate vehicle access to the existing unloading hopper

Piling works including supply, installation and testing of precast reinforced concrete piles and steel piles

Footing and superstructure concrete works including supply and installation of concrete blinding under on ground footings and slabs

Supply, testing, bending, and fixing steel reinforcement in place

Supply, installation and testing of concrete footings, columns, beams and slabs including all formwork, jointing and curing

Stormwater drainage works including supply and installation of new pipework, junction boxes and gross pollutant traps

Water and fire water works including supply, replacement and installation of new pipework valves, mains and connections

Decommissioning and relocation of existing electrical services

Outcomes


BMD Constructions worked collaboratively with the client and adjacent contractors to progressively hand over works as each individual silo reached completion, allowing for early access to each of the areas for the successive packages of works. Through this initiative, as well as the acceleration of preliminary activities, BMD Constructions reached practical completion three months ahead of schedule.

The tight project footprint and shared site posed challenges for the team throughout works, which was managed through collaborative workshops and agreed controls as part of a Safe Work Access Plan. The team were also committed to safety excellence and implemented sign on points at each individual work front. These points required all employees to contact the area owner before entering to ensure all specific risks and controls for the area were understood. This approach to safety resulted in the project being delivered with no lost time injuries.